RBC Installation Contract West & South

This contract included the manufacture, delivery, installation, testing and commissioning of a process plant for RBC plants and all ancillary and control plants.

The contract entailed the upgrading of over twenty wastewater treatment works of design populations between 250 and 2,600. The work was released in three phases. Four consultants including ourselves were involved in the design of these schemes with two responsible for project management. The portion of the contract managed by Doran Consulting included the following wastewater treatment works:

  • Fintona WwTW
  • Fivemiletown WwTW
  • Kilcoo WwTW
  • Lisbellaw WwTW
  • Blackskull WwTW
  • Glassdruman WwTW
  • Tamnamore WwTW 
  • Bellanaleck WwTW
  • Belcoo WwTW
  • Beragh/SixmilecrossWwTW
  • Clady WwTW
  • Drumcard/Derrylester WwTW
  • Clanabogan WwTW
  • Ballinamallard WwTW